About Us

Established in 1984, Keda Group has 42 member companies including Keda Group Co., Ltd.

We provide sustainable renewable energy for everyone
Group Industry

Keda Group has set up subordinate organizations in Beijing, Shanghai, Shenzhen, Hangzhou, Yantai, Qingdao, Binzhou, etc. and set up engineering project offices in 12 provinces and cities in China.

We provide sustainable renewable energy for everyone
Corporate Culture

Develop by technology, establish Keda brand, provide quality products and satisfy customers.

We provide sustainable renewable energy for everyone
Contact Us

Advocate the corporate spirit of hardworking, selfless contribution, dedication and patriotism, pursuit of excellence.

We provide sustainable renewable energy for everyone
Base Infrastructure
Home / Group Industry / Base Infrastructure
Dongying Kendong Seawall Project

The medium scale project is 6.78km long. The seawall is expected to provide effective defense against big tides that will happen once in 50 years. The seawall is 4.6m high and the wave wall is 5.7m high. The side slope at the upstream face is 1:2.75; the upper part of the side slope at the downstream face is 1:2 and the lower part is 1:3. The main seawall is paved with 21cm thick 0.5×0.8m prefabricated concrete plate, with 400g/m2 geotechnical cloth and medium sand subbase of 0.1m thick paved under the plate. The net width of the asphalt concrete pavement is 7 meters.

The planned investment of the project of 34.92 million Yuan:
The first section: pile number from 21+900~24+160, planned investment 11.82 million Yuan.
The second section: pile number from 24+160~28+526, planned investment 23.10 million Yuan.
The project started on May 20th, 2004 and was completed on September 15th, 2005.